Explain site plan and key plan.
Site plan
- The purpose of site plan is to exactly locate the property with reference to the existing properties in all four directions on very adjacent land.
- Site plan also shows the land boundary, margins, construction area, streets, buildings on adjacent lands, service lines like water supply, drainage, power supply, telecommunication, data lines, etc.
- The boundary area of ownership is highlighted by hatching lines.
- The scale may vary from 1 in 500 to 1 in 1000 depending upon the size of land under ownership.
Key plan
- The purpose of key plan is to locate the site of construction in region.
- Person can use key plan to reach.
- The plan shows main roads and well-known buildings as landmark to reach the site.
- Key plan should cover area of 2 km radius around the site.
- Key plan are drawn to the scale of 1 in 10,000.
- The area covering the property is highlighted with hatching lines.